How to plan a home renovation in Lagos, step by step
A practical, step-by-step guide to renovating a home in Lagos: setting goals, budgeting, design, approvals, choosing a builder, buying materials and surviving the work.

Renovating a home in Lagos can be exciting and exhausting in equal measure. Materials change price, builders juggle several sites, the rainy season arrives on its own schedule, and decisions pile up faster than you expect. The difference between a renovation that goes smoothly and one that drags on usually comes down to planning.
This guide breaks the process into clear steps, in the order we’d recommend. Whether you’re refreshing a flat in Yaba, remodelling a duplex in Lekki or reworking a family house in Ikeja, the same principles apply.
Step 1: Be clear about why you’re renovating
Start with the problems, not the finishes. Write down what isn’t working. Maybe the kitchen is too small for how your family cooks. Maybe there isn’t enough storage, so every surface is cluttered. Maybe the bathrooms leak, the wiring is old, or the living room is dark and hot in the afternoon.
Then write down what you’d like the finished home to do for you. More space for guests? A quiet place to work? A kitchen you enjoy cooking in? A home that’s easier to clean? These goals become the brief, and every later decision can be checked against them.
It also helps to think ahead. Are children growing up? Will an older parent move in? Are you planning to sell or rent out the property in a few years? A renovation for your own long-term home looks different from one aimed at resale or short-let income. If letting is the plan, read our guide to designing a short-let apartment in Lagos.
Step 2: Understand what you already have
Before you plan changes, find out what you’re working with. Old buildings can hide surprises: wiring that isn’t safe, plumbing that has been patched many times, damp coming through walls, or cracks that need an engineer’s opinion.
If you have the original drawings, find them. If not, a measured survey of the space is worth doing early. It means your design is based on real dimensions rather than estimates, which saves money when the work begins.
For flats and estates, check what you’re allowed to change. Many estates and building managers have rules about structural work, external changes, working hours and where materials can be stored. Some changes may also need approval from the state’s planning and building authorities; in Lagos, these include the physical planning and building control agencies. Your architect or engineer can tell you what applies.
Step 3: Set a realistic budget, with a contingency
Decide what you can comfortably spend before you design anything. Then set aside a contingency, often around ten to fifteen percent of the total, for the surprises that almost every renovation brings. In older buildings, the contingency is rarely wasted.
Your budget will usually need to cover:
- Design fees and any engineer or architect fees.
- Demolition and removal of rubbish.
- Building work: walls, ceilings, plastering, screeding.
- Electrical and plumbing work, including new circuits for inverters and backup power.
- Materials: tiles, paint, joinery, worktops, sanitaryware, lighting.
- Labour for each trade.
- Furniture, curtains, rugs and accessories.
- Somewhere to stay if you can’t live at home during the work.
Prices of imported materials in Nigeria can move with the exchange rate, so lock in quotes where you can and buy key items early. We’ve written a full guide on how to budget for interior design in Nigeria.
Step 4: Get the design done before the work starts
This is the single most important step, and the one most often skipped. Starting work before the design is finished leads to decisions being made on site, under pressure, by whoever happens to be there. That’s when things go wrong.
A complete design should cover the layout, every wall and ceiling change, where each light, switch and socket goes, the kitchen and bathroom layouts, all the finishes, and any made-to-measure joinery. At Suiiel, we show you every room in realistic 3D so you can see and agree the design before anything is bought or built. That’s explained in why we show you your home in 3D.
Once the design is agreed, it should be turned into clear drawings and a schedule of finishes. These are what you’ll use to get accurate quotes and to keep everyone on site working from the same information.
Step 5: Choose your builder carefully
Ask for recommendations, look at finished work, and if possible speak to previous clients. A good builder will want to see the drawings before quoting, will ask questions, and will explain what is and isn’t included.
Get more than one quote, but compare them carefully. The cheapest price often leaves things out, which then appear later as extras. Ask each builder to price the same drawings and schedule, and to list what’s excluded.
Agree in writing:
- The scope of work, based on the drawings.
- The price, and what happens if the scope changes.
- A payment schedule linked to completed stages, not dates.
- A realistic programme, with the main milestones.
- Who buys which materials, and who is responsible if they’re damaged.
- How the site will be kept safe, secure and clean.
Step 6: Plan the order of works
Renovations follow a natural order, and doing things out of sequence costs money. Broadly, it goes:
- Protection of anything that’s staying, then demolition and strip-out.
- Structural work, if any, checked by an engineer.
- First fix: new wiring, plumbing pipes, and anything hidden in walls and ceilings.
- Walls, ceilings, plastering and screeding.
- Waterproofing in wet areas, then tiling.
- Joinery: kitchens, wardrobes, doors.
- Second fix: switches, sockets, light fittings, taps and sanitaryware.
- Painting and decorating.
- Cleaning, snagging, then furniture and finishing touches.
Think about the season too. Heavy rain can delay external work, roof repairs and anything that needs to dry. If your renovation includes these, plan them for drier months where possible.
Step 7: Order materials early
Long lead times are one of the biggest causes of delays. Imported tiles, sanitaryware, lighting and specialist fittings can take weeks or months to arrive. Made-to-measure joinery takes time to build. Order these as soon as the design is fixed, and check items carefully when they arrive, before the builder needs them.
Keep a simple spreadsheet listing every item, the supplier, the price, the order date, the expected delivery and where it’s going in the house. It sounds tedious, but it saves a great deal of confusion.
Step 8: Stay involved during the work
Visit site regularly, or have your designer do it for you. Check that what’s being built matches the drawings, and raise questions early. A socket in the wrong place is a five-minute fix before plastering and a messy job afterwards.
Keep decisions in writing, even if it’s just a WhatsApp message confirming what was agreed. Changes are normal, but each one should be priced and agreed before it’s done.
If you’re overseas, you’ll need someone you trust on the ground. We explain how to manage this in building a home in Nigeria from abroad.
Step 9: Snag before the final payment
When the builder says the work is finished, walk through every room slowly with the drawings and a notebook. Check tiles for evenness and cracks, doors and drawers for smooth movement, paintwork for patches, every light and socket, every tap and drain, and the sealant around sinks and showers.
List anything that isn’t right and agree a date for it to be fixed. It’s normal to hold back a small final payment until the snagging list is complete.
Step 10: Furnish and live in it
The final stage is the most enjoyable: furniture, curtains, rugs, lamps and art. If you planned the furniture as part of the design, you’ll know exactly what fits where. Some pieces may be made to measure, which is often the best way to make an awkward wall or alcove work. Read more in why made-to-measure furniture is worth it.
Living through a renovation
If you’re staying at home during the work, plan it like a project of its own. Agree which rooms will stay usable, set up a temporary kitchen corner with a fridge, kettle and microwave, and pack away anything that dust could damage. Dust from cutting tiles and sanding plaster gets everywhere, so seal doors to finished rooms with plastic sheeting. Agree working hours with the builder and keep neighbours informed; it makes life much easier.
Common mistakes to avoid
- Starting work before the design and drawings are finished.
- Choosing finishes one at a time, in a hurry, at the showroom.
- Forgetting the electrical plan, then finding sockets in the wrong places.
- Not planning for backup power. If you want solar, speak to an installer like ATOM Energies before the walls are closed up.
- Paying in large amounts upfront rather than by completed stages.
- Having no contingency in the budget.
- Underestimating how long imported items take to arrive.
The short version
Know why you’re renovating, understand the building, set a budget with a contingency, finish the design before work starts, choose your builder carefully, order early, stay involved and snag properly. It sounds like a lot, but each step makes the next one easier.
If you’d like help planning a renovation in Lagos or anywhere in Nigeria, tell us about your home. We can design it, show it to you in 3D, prepare the drawings your builder needs and visit site as the work goes in.